2019 Refinery Maintenance Schedule RUP Maintenance to start on February 26, 2019. Unit Plt 100 Crude Oil İzmir Plt 9200 CCR Quarter Duration (weeks) Reason Q4 2-3 Periodic Maintenance Q1 2-3 Periodic Maintenance Q1&Q2 12-13 Detailed Maintenance RUP İzmit Plt 2 Crude Oil & Vacuum Unit Q4 7-8 Periodic Maintenance Plt 7 FCC Q4 5-6 Periodic Maintenance Kırıkkale Batman Plt 1100 Crude Oil & Vacuum Unit Q1&Q2 *3-4 Periodic Maintenance * Total duration allocated among quarters Investor Presentation www.tupras.com.tr OUTLOOK RUP Maintenance Preparation and planning phase: 2018 Maintenance Start: Feb 26 Catalyst changes Checks on distillation columns, heat exchangers and furnaces Detailed planned maintenance Completion: planned as late May 2019 46