2019 Refinery Maintenance Schedule
RUP Maintenance to start on February 26, 2019.
Unit
Plt 100 Crude Oil
İzmir
Plt 9200 CCR
Quarter
Duration
(weeks)
Reason
Q4
2-3
Periodic Maintenance
Q1
2-3
Periodic Maintenance
Q1&Q2
12-13
Detailed Maintenance
RUP
İzmit
Plt 2 Crude Oil & Vacuum Unit
Q4
7-8
Periodic Maintenance
Plt 7 FCC
Q4
5-6
Periodic Maintenance
Kırıkkale
Batman
Plt 1100 Crude Oil & Vacuum Unit
Q1&Q2
*3-4
Periodic Maintenance
* Total duration allocated among quarters
Investor Presentation
www.tupras.com.tr
OUTLOOK
RUP Maintenance
Preparation and
planning phase: 2018
Maintenance Start: Feb 26
Catalyst changes
Checks on distillation columns, heat
exchangers and furnaces
Detailed planned maintenance
Completion:
planned as late May 2019