Endeavour Mining Results Presentation Deck
KEY GROWTH PROJECTS
Sabodala-Massawa expansion underway; progressing DFS on greenfield projects
BROWNFIELD PROJECT:
SABODALA-MASSAWA EXPANSION
DFS INSIGHTS:
Construction to commence in Q2-2022, first
gold pour from the BIOX® plant expected in
early 2024
■ Incremental annual production of 194koz
over next five years at a low AISC of $531/oz
■ BIOX® project Capex: $290m
After-tax NPV 5% & IRR at $1,500/oz: $861m,
72%
■
Lifts Sabodala-Massawa complex to top tier
status
GREENFIELD PROJECT:
LAFIGUÉ ON FETEKRO PROPERTY
PFS INSIGHTS:
■
Mine life: 10 years
■ LOM AISC: $838/oz
PANGOR
▪ Average annual production: 209koz
Initial Capex: $338m
▪ After-tax NPV5% & IRR at $1,500/oz:
$497m, 33%
DFS due Mid-2022
PFS INSIGHTS:
■
Mine life: 11 years
■ LOM AISC: $901/oz
■
ENDEAVOUR
GREENFIELD PROJECT:
KALANA
MINING
Average annual production: 150koz
Initial Capex: $297m
After-tax NPV 5% & IRR at $1,500/oz: $331m,
49%
▪ Acquisition price: circa $120m
DFS due H2-2022
14View entire presentation