Project Development Timeline Sithe Global has spent over 6 years developing this Project MOU Signed between GoG and Synergy / Harza/MWH, 4/98 Project development delayed due to privatization of GPL and resumption by GOG, 2002- 2005 Synergy identified Sithe Global as potential investor, 4/07 Framework Project Agreement initialed with IDB signs mandate letter, 9/12 Lenders begin final diligence, documentation 1/13 Target financial close EPC bid proposals come in from 5 qualified bidders, 10/08 Synergy transferred Interim License to Sithe Global 10/09 Agreement with China Development Bank, 7/10 GOG, 6/11 1998-2002 2003-2006 2007-2008 2009 2010 2011 2012 2013 Synergy/ Harza / MWH submit feasibility report to GoG, 12/01 China Railway chosen as EPC contractor, 12/08 EPC price reduced from original bid price, 12/09 12 ESIA completed EPC contract executed, 9/12 Target to begin construction SITHE GLOBA