Elkem Company Overview and Financials
Project schedule with planned production start-up in H1
2024
Project timeline
Highlights from evaluation1
2019
2020
2021
2022
2023
2024
FEL1,2
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Execution
FEL3
Approval long lead (CWS)
Detail design
Project approval
Procurement / fabrication
Construction
Commissioning / start up
Production ramp-up
Full production
in 2026
Elkem 1) Analysis performed by Independent Project Analysis Inc. in February 2021 (IPA: Prospective Evaluation Prepared for Elkem ASA February 2021)
IPA Prospective Evaluation
Status of Project Drivers
Objectives and Teams
Project Planning
Fair
Good
Objectives Are Clear
Team Is Integrated
FEL Index
Poor
Estimating & Planning for Control
Fair
Poor
Best Practic
Project Control Index
Defi
Prepared for Elkem ASA
February 2021
Internal assessments highly in line
with the findings in the IPA -
no red flags for the project
28View entire presentation