Economic Potential of DACCS and Global CCS Progress
5.8 TIMELINES FOR CCS
PROJECT DEVELOPMENT
YEAR
APPROVALS
Geological storage exploration permitting
Geological storage resource declaration
as
Building a new CCS facility or retrofitting
CCS to an existing facility is a major
industrial project requiring the full
suite of studies, from concept through
pre-feasibility and feasibility, before
detailed engineering studies commence.
The complexities of identifying and
negotiating commercial agreements
with counterparties where required
(for example, CO2 offtake agreements)
and completing environmental impact
assessment processes, as well
obtaining the necessary tenements
and approvals for geological storage of
CO2 from regulators, generally requires
years to complete. This is assuming that
appropriate legislation for the regulation
of CCS has been promulgated; in most
jurisdictions, this is still not the case. The
development of a CCS project shares
many similarities with mining and mineral
processing and oil or gas production
projects; a large complex CCS project
may take a decade to progress from
concept to operation.
GEOLOGICAL
STUDIES
CO2 CAPTURE
& TRANSPORT
STUDIES
CONTRACTING
PROJECT
EXECUTION
Environmental Impact Assessment
& Approvals
Geological storage injection permitting
Basin Screening (desktop)
Initial Inventory Review (desktop)
Storage Site Identification & Appraisal
(data collection)
Storage Field Development
& Engineering Design
CO2 Capture & transport Scoping
& Pre-feasibility Studies
CO2 Capture & Transport Feasibility Studie:
CO2 Capture & Transport FEED Studies
Financial Investment Decision
Counterparty Commercial Negotiations
CO2 Capture & Transport
Detailed Engineering
Procurement
[47]
Construction
Commissioning
Operation
FIGURE 28: SIMPLIFIED GANTT CHART FOR A COMPLEX CCS PROJECT
1
2
NI
MI
H1 H2 H1 H2 H1 H2
4
H1 H2
IG
6
5
H1 H2 H1
7
8
H2 H1
H2 H1
I
H2
9
H1
H2
GLOBAL CCS
INSTITUTEView entire presentation