ENGIE Investor Presentation FUTURE PROJECTS OF RENEWABLE ENERGY (1/2) Punta Lomitas Wind farm Ica Max. Power: 260 MW CAPEX: Aprox. 300 MUSD • Mar 2021: Definitive Concession of Generation and Transmission • Aug 2021: Easement from government • 2H 2021: Construction begins • 2Q 2022: First energization (*) • 1Q 2023: Commercial Operation Date (COD) (*) The project also entails the installation of 50 wind turbines SG5.0-145 MKII; one 220kV GIS substation; one 220kV overhead line (double circuit) of 60km; one 220kV AIS substation (double bus bar). (*) Tentative ENGIE Energía Perú 21