Renewable Energy A (i) Standalone (Ownership Based) (b) Tender Stage 21 एनएचपीसी NHPC Estimated S.No Name of Project Capacity (MW) Expected Capital cost Commissioning (in Crs.) Schedule Tentative Tariff (Rs./unit) Status of PPA 1 Development of 75 MW capacity ISTS connected Solar Power Project anywhere in India for sale of power through Power Exchange 75 430.00 2024-25 2.82 NA 2 Floating Solar Kerala (50MW), West 50 326.00 2024-25 3.82 PPA under exploration Kallada 3 200 MW Grid Connected Solar photovoltaic Power Projects located in 600. MW Solar Park at Khavda, Gujarat 200 1100.00 2024-25 2.73 PPA signed with GUVNL on 10.08.2023 Total-(b) 325 1856.00 Sub Total Standalone (Ownership Based) -A(i): (a+b) 1325 8460.40