Li-Cycle Results Presentation Deck
Rochester Hub: Achieved Engineering, Procurement and Construction
Milestones, Maintaining Commissioning Start Late 2023
Rochester Hub Execution Update
Engineering
Procurement
Construction
~95% of detailed engineering completed
Long-lead equipment on-site in Rochester - crystallizers and solvent extraction
equipment
Largely completed procurement of the majority of bulks, such as steel, cabling and
piping
Major buildings nearing completion.
Advanced steel and concrete installation; ~40% complete with the steel
construction of the utility pipe racks and accelerating pouring of concrete
foundations for tank installations
Mechanical and electrical equipment installation underway, including electrical
rooms, tanks, crystallizers and solvent extraction equipment
ā Focus is on actively managing the construction labor as part of the Rochester Hub
construction budget of $560 million
Li-Cycle 10View entire presentation