Li-Cycle Results Presentation Deck

Rochester Hub: Achieved Engineering, Procurement and Construction Milestones, Maintaining Commissioning Start Late 2023 Rochester Hub Execution Update Engineering Procurement Construction ~95% of detailed engineering completed Long-lead equipment on-site in Rochester - crystallizers and solvent extraction equipment Largely completed procurement of the majority of bulks, such as steel, cabling and piping Major buildings nearing completion. Advanced steel and concrete installation; ~40% complete with the steel construction of the utility pipe racks and accelerating pouring of concrete foundations for tank installations Mechanical and electrical equipment installation underway, including electrical rooms, tanks, crystallizers and solvent extraction equipment ā˜ Focus is on actively managing the construction labor as part of the Rochester Hub construction budget of $560 million Li-Cycle 10