Path to recover production: 2022 key milestones
Iron ore production
Copper production
Mt
kt
316
320-335
2021
2022E
▪ Improvement of S11D performance with
jaspilite crushers and mobile crushers.
▪ Higher quality product portfolio
Tailings' filtration plants and start-up of
Torto dam and raising of Itabiruçu dam
(taking capacity to 370 Mtpy)
297
2021
■
330-355
2022
▪ Stable production at North Atlantic
mines (Sudbury + Totten ramp up)
▪ Improvement in Salobo mine
movement and startup of Salobo 3
Planned maintenance at Sossego
Nickel production
kt
168
I
2021
175-190
2022
De-risking
Stable production at North Atlantic
mines (Sudbury + Totten ramp up)
▪ New projects: VBME and CCM 1
Onça Puma stabilization
▪ PTVI furnace rebuild
my