NewFortress Energy 2Q23 Results slide image

NewFortress Energy 2Q23 Results

Significant number of projects expected to come online (10) in next few months(11) Project FLNG 1 Puerto Rico power Barcarena Executive Summary We are at an inflection point as $3.2bn of infrastructure(8) comes online (10) in the next ~90 days(11) Santa Catarina La Paz Description 1.4 MTPA liquefier 150 MW Palo Seco; 200 MW San Juan 3 MTPA LNG terminal 3 MTPA LNG terminal 135 MW power plant Investment (8) $1.3bn $500mm $700mm $500mm $200mm Expected (11) COD(10) Sep. 2023 May 2023; September 2023 Dec. 2023 Jan. 2024 Aug. 2023 $3.2bn of infrastructure(8) being converted from construction to revenue producing Significant positive impact on the company LO 5