Freyr SPAC Presentation Deck
FREYR Battery Manufacturing Facility Development
Installed Capacity
GWh
90
80
70
60
50
40
30
20
FREYR's Phased Gigafactory Development: 80+ GWh Installed by 2028
10
2022
2025 Target Installed Capacity: 43 GWh
2023
2024
FREYR
Clean battery solutions
2025
2028 Target Installed Capacity: 83 GWh
Gigafactory 2
Gigafactory 1
Gigafactory 3
2026
Joint Venture Gigafactory 1
Gigafactory 5
Gigafactory 4
Joint Venture Gigafactory 2
2027
Gigafactory 6
2028
Note: Company projection based on 24M data; the indicated outlook should not be construed as estimates or guidance for future developments of the Company
1) Capacity refers to 80% of nameplate capacity for Gigafactories and 100% of nameplate capacity for Joint Venture Gigafactories
2029
Asset
Customer Qualification Plant
Gigafactory 1
Gigafactory 2
Joint Venture Gigafactory 1
Gigafactory 3
Gigafactory 4
Gigafactory 5
Joint Venture Gigafactory 2
Gigafactory 6
TOTAL
Capex
($ millions)
$35
$275
$310
$565
$380
$380
$775
$565
$775
$4,060
Capacity ¹)
(GWh)
0.2
5
8
8
11
11
16
8
16
83
Operational
Start
2022
2023
2024
2024
2025
2025
2026
2027
2028
Source: Company data