Freyr Investor Day Presentation Deck
CQP production plan overview
Progress at the CQP drives process and technology validation with our customers and capital providers
Progress Plan/Key Milestones
First cells produced: June 25th, 2023
• Manual casting and merging
• All else automated
Sample production targets: 3Q/4Q 2023
• All processes automatic
• Improve yields, uptime and yields
Targeted approval of first samples
Fully integrated production line: 4Q 2023
Target approval of operating parameters
Continuous improvements: 1Q 2024
FREYR
# of CQP cells producedper week
CQP Production Plan: 3Q 2023 - 1Q 2024
Sept. 2023
Oct. 2023
Sample production
Oct. 2023
TARGET - # Good cells
Start continuous
casting
Nov. 2023
Dec. 2023
Increasing
production speed
and quality
TARGET - #All Cells
Jan. 2024
Stabilizing and
validating giga
scale
Feb. 2024
Forecasted Line speed
Mar. 2024
Production Line Speed (Meters/minute)
11View entire presentation