Following the successful build-up of our 0.4 GW capacity,
we are continuing our international capacity growth
Cell and module production
Meyer Burger planned installed nameplate production
capacity, year-end [GW]
Cell Module
1.4 1.4
1.0 1.0
0.4 0.4
3.4 3.4
2021
2022
2023e
2024e
4.1 4.1
2025e¹
6.9 6.9
2026e1
1) Scenario, depending on policy
support, e.g. EU Innovation Fund
Roadmap:
•
•
•
Approximately 1 GW cell and module
nameplate capacity installed in Thalheim
and Freiberg, Germany, respectively, in
2022
A further ~0.4 GW cell and module
capacity expected to become available at
the same German sites in 2023
Expansion by another ~2 GW of cell
production in Colorado Springs, U.S. by
2024, and module production in
Goodyear, Arizona planned (thereof up to
1.4 GW for long-term offtake with DESRI,
BayWa and Ingka)
MEYER BURGER