Fresnillo Results Presentation Deck

SAN JULIÁN ● ● ● ● ● CIÉNEGA Operationally in-line with expectations Labour reform impacted development rates and equipment availability in 2H21 Lower volume of ore processed impacted by an electrical outage during the year ● 2021 PRELIMINARY RESULTS - OPERATIONS OTHER OPERATIONS ● HERRADURA Strong operational performance As the scope of the Carbon in Column project increased, construction will now be finished in mid 2022 Concluded the conversion of our haulage fleet to the dual fuel system ● Strong operational performance Higher than expected ore grade at the DOB Operational continuity of the DOB mine was maintained, with no geotechnical issues detected Lower volume of ore processed driven by two electricity outages during the year ● NOCHE BUENA The mine closure plan commenced, with ore extraction from the pit expected to end mid- 2022 15