Origination - Project Timeline to Completion ¹ A Extended Project Timelines Create Challenges Altus Power's Self-Developed/Construction Historical Timeline 12-15 months Current Timeline Extension 3-6 months Channel Partner Fully Developed/Construction Historical Timeline 6-9 months Current Timeline Extension 3-6 months 1 All references to timelines refer to time between terms agreed until commercial operations and is based on our historical business operations. There is no guarantee that projects developed in the future will follow the same timeline as our historical operations 15