Vale Investor Presentation Deck
D
Maximize flight to quality in Iron Ore
Resuming 400 Mtpy iron ore capacity is a careful
and complex task
Northern
System
Southeastern
System
Southern
System
Ramp-up and
open new
mining fronts
Develop filtering
and dry stacking
capacity
Solve
interference of
upstream dams
●
• Serra Leste
North 240 Mtpy
●
·
●
New assets and solutions
coming online
●
• Gelado project
Serra Sul 120
Timbopeba pit
Torto dam
Filtering plants in Brucutu and Itabira
Filtering plant in VGR
Maravilhas III dam
●
Forquilha V dam
Production and capacity (Mtpy)
302
189
73
38
-2-
2019 Production
(after
Brumadinho)
322
206
61
53
-2-
Capacity by
the end of
2020
Northern System
Southeastern System
400
230
101
67
-2-
Capacity by
the end of
2022
Southern System
Midwestern System
15View entire presentation