REE SPAC Presentation Deck
Production Roadmap
Key Events
Engineering Design
Production Intent
Pilot Manufacturing
Purchasing
Proof of concept
Design Validation
Alpha Verification
Beta Verification
Pilot Capability
Build Units
RBE
2020
Q1
Q2
Vendor approval & RFQ
Q3
Validation & Verification
Completed
Confidential and Proprietary Information
Q4
2021
In progress
Q1
Q2
Q3
1st Engineering Center
Established - UK
Q4
EC Lead
2022
Q1
First IC Established
U.S.
Vendor Networks Validated
Safe Launch factory and process template
Samples
Build 1
EC Lead
Q2
Product & systems engineering center driving customer program management & delivery
Verify
Q3
LFS
Q4
2nd IC Established
Germany
2023
OTOP
Q1
Q2
Serial production supply and network optimization
Rampi
Q3
3rd IC Established
Japan
globally 15k units
Q4
2024
Q1
4rt IC Established
TBD
Q2
Q3
Ramping Globally 110k units
(1) Timing and locations represent management expectation and are subject to change. These projections are for illustrative purposes only and should not be relied upon as being necessarily indicative of future results
Q4
31View entire presentation