Fresnillo Results Presentation Deck
●
●
●
●
●
2021 PRELIMINARY RESULTS
JUANICIPIO (JV WITH MAG SILVER. FRESNILLO: 56%)
The construction of the Juanicipio plant was delivered on
schedule during 4Q21
Now focusing on complying with the new requirements from
the state owned electricity company and the energy regulator
to complete the tie-in to the national power grid. As a result,
the mill commissioning timeline was extended by
approximately six months
Two of the four power shutdowns completed, two more to go
before the tie-in
To mitigate potential adverse effects, Fresnillo will make
available any unused plant capacity at its Fresnillo and
Saucito operations to process material produced at Juanicipio
The plant is expected to achieve 85-90% of nameplate
capacity by the end of 2022
Commissioning of Juanicipio will drive increased silver
production and lower consolidated group costs