Fresnillo Results Presentation Deck

● ● ● ● ● 2021 PRELIMINARY RESULTS JUANICIPIO (JV WITH MAG SILVER. FRESNILLO: 56%) The construction of the Juanicipio plant was delivered on schedule during 4Q21 Now focusing on complying with the new requirements from the state owned electricity company and the energy regulator to complete the tie-in to the national power grid. As a result, the mill commissioning timeline was extended by approximately six months Two of the four power shutdowns completed, two more to go before the tie-in To mitigate potential adverse effects, Fresnillo will make available any unused plant capacity at its Fresnillo and Saucito operations to process material produced at Juanicipio The plant is expected to achieve 85-90% of nameplate capacity by the end of 2022 Commissioning of Juanicipio will drive increased silver production and lower consolidated group costs PROJECTS Beneficiation plant Milling area ▬ Flotation cell lines - Lead and Zinc Electrical sub-station 16