Fresnillo Results Presentation Deck
2022 PRELIMINARY RESULTS OPERATIONS
OTHER OPERATIONS
SAN JULIÁN
Silver production at San Julián veins saw a higher ore grade due to
the prioritisation of extraction from wider veins of the mine with higher
silver content but lower gold ore grade
Exploration continued in the area, increasing silver resources at San
Julián veins and DOB
Construction of the third phase of the tailings dam commenced
CIÉNEGA
146
• Ongoing workforce rotation, together with lower equipment availability
from contractors, continued impacting productivity
87,503 metres drilled during the year, although higher costs and cut off
grades resulted in a decrease in silver and gold resources by 10.8%
and 14.3% respectively
Mo
Construction of the second stage of the third tailings dam commenced
15
HERRADURA
As the scope of the Carbon in Column project was increased to
improve its efficiency, construction will be completed in mid-2023
The pit slope optimisation study was concluded and
recommendations are being tested in different geotechnical
domains of the pit
echnical
Construction of the 14th phase B leaching pad was concluded
●
NOCHE BUENA
Additional mineralisation was found through the condemnation
drilling and mining was extended for a few additional months
Productivity increased due to the increase in tonnes hauled shorter
distances by a reduced number of employees
The mine closure plan underwayView entire presentation