Vale Results Presentation Deck
Vale's Performance in 2022: We are building a better Vale
Upstream dams in Brazil: 40% eliminated by 2022E
Baixo João Pereira dam and Dike 4¹:
decharacterization concluded
Backup dam for Coqueirinho
completed
B3/B4: 40% tailings removed, and
conclusion anticipated to 2025²
9 structures eliminated since 2019
Eliminated upstream structures in Brazil
Unit per year
7
5
532
2
40%
4
2
60%
2
2
5
Concluded
3
30
2019-21 2022E 2024E 2025E² 2026E² 2027E 2029E 2035E Total
¹ Dike 4 decharacterization was completed and final works in the site will continue along the second half of this year. 2 Due to the need to implement instruments, drilling and complementary engineering studies, the date of
Campo Grande de-characterization conclusion changed from 2025 to 2026. Despite the change in the Campo Grande dam de-characterization deadline, the company maintains the commitment to de-characterize 18 structures of
the program by 2025 due to the tendency to anticipate the completion of the B3/B4 dam works.
VALEView entire presentation