Vale Results Presentation Deck
We are progressing on resumption plan
Iron ore capacity (Mtpy)
318
327
330
335
343
380
400
||
Investor 1Q21 2Q21 Today End of End of
Tour 2020
2021
2022
¹ Previously, Itabira was expected to negatively impact Vale's capacity in 7 Mtpy.
450
Future
Recent developments
April
2021
May
2021
July
2021
Potential
setbacks
Northern System
Southeastern System
Southern System
• Fábrica: Temporary authorization for wet processing
facilities tests (+4 Mtpy).
Serra Leste: Site reached full capacity (+2 Mtpy)
•Brucutu: Increase of high-silica sinter feed production
by dry processing taking advantage of market
conditions (5 Mtpy of net addition on capacity).
• Fábrica: Final authorization to operate beneficiation
and pelletizing plants.
• Vargem Grande: Start-up Maravilhas III dam (4 Mtpy
of net addition on capacity).
• Itabira: Temporary tailings disposal restrictions due to
limited disposal areas (-2 Mtpy¹).
• Temporary restrictions and licensing: Mutuca,
Northern System and others (-5 Mtpy).