Vale Results Presentation Deck slide image

Vale Results Presentation Deck

We are progressing on resumption plan What is next? 3Q21 4Q21 Delays to 2022 Vargem Grande Unlock conveyor belt S11D Second crushers' installation to process jaspilite ores Brucutu Torto dam start-up +6 Mtpy +2 Mtpy +12¹ Mtpy Northern System Southeastern System Southern System Itabira Start-up of Conceição filtration plant, softening short term tailings disposal restrictions +0 Mtpy in short term ¹ Brucutu site capacity increased in 2Q21 to 16 Mtpy (+5 Mtpy of net addition) with increase of high-silica sinter feed production by dry processing, taking advantage of market environment. As a result, the net addition capacity from the Torto dam start-up changed to 12 Mtpy (from previous 17 Mtpy). VALE 13