2. Progress after the 1st Review Mission
About 1st "Application” submitted on 21st Dec. 2021
➤ After the 1st review mission, NRA continued the examination of "Application"
➤ When NRA secretariat prepared the draft review results document, NRA
secretariat reported to the NRA Commission for their discussion and
consideration at open meeting.
Then NRA solicited public comments on the draft result of the review and
considered whether the submitted comments should be reflected.
✓ Public comments done from 19 May 2022 to 17 June 2022 (30 days)
✓ The number of submitted comments were 670 (Total number of comments were 1233)
After considering those comments, NRA concluded that the "Application"
satisfies the relevant items of the Regulatory Requirements and approved the
"Application".
After the approval of "Application", NRA has explained our confirmation points
and results during the examination and review process to local stakeholders,
neighboring countries.