CAMBODIA'S TRANSMISSION LINE DEVELOPMENT PLAN 2018 - 2025
List of transmission projects under the 2018 - 2025 Transmission Development Plan:
Project Name
Length
(km)
Target
Operational
Year
Project Name
Length
Target
(km) Operational Year
230 kV Transmission Line
115 kV Transmission Line
GS2
GS Hun Sen Park and Grid
2019
Substation
GS Rottanak Mundul - GS Pailin
45
GS3 GS Toul Kork
GS5 GS Chroy Changvar
18
558
2019
GS Battambang - East Siem Reap -
Kampong Thom - Kampong Cham
Phnom Penh Loop Line Phase 2 (NPP -
Chroy Changvar - EPP - NPP)
350
2019
96
2019
2019
2019
Tatay Hydropower - Phnom Penh
GS Koh Kong - GS Koh Kong City
182
2019
20
2019
GS Kampong Cham - GS Praek Prosab
91
2019
(Kratie)
GS Svay Antor - GS Kampong Soeung
46
GS Preah Sihanouk - GS Ream
GS Ream GS Chamkar Luong
-
GS Kampong Thom - GS Preah Vihear
Underground Line from GS1 - GS EDC
-
HQ GS Samdech Hunsen Park - GS
Olympic Stadium - NCC - GS3
6269
2019
GS Chamkar Luong - GS Botumsakor
GS Botumsakor - Tatay Hydropower
GS Kratie GS Mondulkiri
54
2019
70
2019
170
2019
12
2019
GS Ratanakiri - GS Stung Treng
120
2019
60
2019
GS Beak Chan - GS5 - NCC
20
2021
GS4
GS Kampong Speu (New) - GS
140
2019
48
2021
Kampong Speu
GS Stung Hav - GS Outres
16
2021
14
14
2020
GS Suong GS Svay Antor
45
2021
GIS2-GS Prek Hou
15
2021
GS Prek Prosab - GS Kratie
GS Krolanh GS Oddor Meanchey
GS Chamkar Luong - Kirirom III Hydro
Power
383
30
GS 5 GS Sensok
6
2022
80
2021
GS Steung Treng - GS North Siem Reap
200
2025
30
2024
GS North Siem Reap - GS East Siem Reap
44
2025
GS Kampot -GS Chip Mong
46
2024
Sub-total 1,456
GS Chrak Mates - GS Pornhea Krek
75
2025
500 kV Transmission Line
GS Pornhea Krek - GS Soung
45
2025
GS7 GS Koh Thom
40
2025
Phnom Penh - Preah Sihanouk
GS Stung Treng - Lao Border
198
2019
55
2021
GS Koh Thom -GS Takeo
45
2025
Sub-total
827
GS Bek Chan - GS East Phnom Penh
Phnom Penh - Soung
45
2021
90
2022
Sub-total
388
Grand Total 2,671
RHB
Source: EDC Annual Report, 2017