Project Overview Capacity: Land: Up to 151.2 MW. • Voluntary wind energy leases and associated facilities easements. Good neighbor agreements offered to everyone within the project boundary and 1/2 mile from a turbine. Proposed Project Footprint To Include: • • Up to 42 turbines in both Grant and Roberts Counties. Access roads, underground 34.5 kV collector lines, underground fiber-optic cables for turbine communications, etc. An operations and maintenance ("O&M") facility. Up to 3 permanent meteorological ("MET") towers. Proposed Project Substation: A 34.5- to 345-kV collection substation. Proposed Project Transmission Line: ~8-mile 345 kV feeder line, connecting the project to the Otter Tail switching station in Mazeppa Township (for access to the new Big Stone South-to-Ellendale 345 kV line). Schedule: • • Start of construction: fall 2019 Commercial Operation Date ("COD"): Fall 2020 3 APEX CLEAN ENERGY