Procurement
Goal: Build an operational CHP system according to specifications,
on schedule and within budget.
• Timeframe: 3 to 30 months, depending on system size and
complexity
Typical Costs: $1,000 - $4,000/ kilowatt (kW) installed
• Candidate site level of effort required: Varies depending on
procurement approach, similar to any construction project
• Questions to answer: Is the system fully commissioned and running
as designed? Will operations and maintenance be performed by site
staff or will it be outsourced? If in-house, have employees been
trained to perform these functions? If outsourced, have service
contracts been procured for equipment or system maintenance,
equipment overhaul or replacement, system availability, or
monitoring and control?
http://www.epa.gov/chp/project-development/stage4.htmlView entire presentation