Investor Presentaiton
9.5 Mtpa
CARDINAL
RESOURCES
KEY ESTIMATED PRODUCTION RESULTS
UNIT
Gold Produced
PFS
PRODUCTION
SUMMARY
☐ Maiden Ore Reserve 4.76 Moz
■ Starter Pit yielding ~900 koz
☐
gold with 0.5: 1 strip ratio
Life of mine strip ratio of 1.4 : 1
Mineralisation 1.1 km long and
350m wide
■ >10,000 oz ounce per vertical
metre at 0.5 g/t cut-off
■
New conventional gold plant
inclusive of conventional
flotation and regrind to CIL
Table Notes:
Gold Price – Financial Model
-
Gold Produced
(Average for full production years) 1
Gold Head Grade
Gold Recovery
Ore Mined
(0.5 g/t cut-off grade)
Strip Ratio
Mine Life
(Inc ramp-up and mine closure)
Development Capital Cost
(Including 15% contingency and owners costs)
1 Excludes ramp-up and for the Life of Mine scenario mine closure (Years where full production is not realised)
Starter Pit
Life of Mine
US$ / oz
1,250
(oz/yr)
361,000
294,000
(oz)
907,000
3,975,000
g/t Au
1.31
1.14
%
86
84
Tonnes
24,000,000
129,600,000
W:O
0.5 1
1.4 1
years
2.5
14
US$ M
414